Gas connection in an apartment: procedure and rules for gasification of housing in apartment buildings

If you are the happy owner of an apartment in a new building, then soon you will have to face the procedure for connecting gas in a new home. Agree, it is better to understand the issue in advance in order to be fully prepared for all possible difficulties.

In this case, the gas connection in the apartment is somewhat different from the gasification of a private house, since apartment buildings managed by a group of people - apartment owners, whose consent is mandatory for connecting the building to the central gas pipeline.

To be able to use gas, the owner of the apartment will need to complete the preparation of the premises for the safe operation of gas equipment. Further in the article, we will reveal the main stages of connecting gas in an apartment, and tell you how to properly prepare your home for the upcoming gasification.

The content of the article:

  • The procedure for connecting to the gas pipeline
    • Gas connection specifications
    • When is the connection made?
  • Basic rules for gasification in an apartment
  • Conclusions and useful video on the topic
instagram viewer

The procedure for connecting to the gas pipeline

If in a private house the owner independently decides on the need to ensure gasification real estate, then in an apartment building for the procedure, the consent of each the owner of the apartment. Only after that you can proceed to the next stages of the project.

Placing a gas boiler in the kitchen

Depending on the number of gas appliances used inside the apartment, technical conditions are calculated for each object on an individual basis.

First of all, the future gas consumer will need to draw up a package of legal documentation, which includes the right ownership of the apartment, as well as a document confirming the consent of the residents to connect the whole house to the central gas pipeline.

This is a prerequisite, since without the listed documents, the homeowner will not be able to obtain technical specifications.

Next, the home owner will need to conclude an agreement with the gas distribution company, and apply for obtaining technical specifications for gas connection. This document confirms the possibility of including a new user in the gas system.

The next stage is the preparation of the premises for the subsequent gas connection, which includes repair work in the apartment. In this case, you will need to fulfill at least the minimum requirements put forward by the gas service.

After carrying out all the repair and installation work, the homeowner will need to call a fireman for ventilation duct checks and drawing up an act. If all the requirements are met, and the safety rules are fully complied with, then the specialist writes out the appropriate act.

Conclusion of a gasification contract

If all documents are correct, then the owner of the apartment can safely conclude an agreement with the gas company on the purchase of gas and maintenance of the gas supply system

At the next stage, the gas is connected in the apartment in the new building, but this is possible only after 50% of the residents of the new building have successfully passed all the above stages. In addition, at the time of connecting the facility to the central gas pipeline, all owners must stay in their apartments.

Gas connection specifications

These requirements are calculated for the safest use of gas equipment, therefore, the fulfillment of technical conditions is a mandatory step for all consumers.

The document contains all the necessary conditions and requirements for the design of the gas pipeline, including its mounting parts, as well as for the chemical composition and technical parameters of the fuel.

Correct fulfillment of technical conditions

Drafting a plug-in system required for the construction of a gas pipeline is impossible without obtaining and further meeting the technical specifications

Different consumers can use gas for completely different purposes, for example, someone has enough gas stoves for maximum comfort, while another resident of the apartment building plans install a gas water heater and additional floor heating. In this case, the technical conditions for each consumer will be drawn up individually.

This stage of gas supply in apartment buildings also includes installation of a gas meter, without which the inspector will not be able to draw up an act. If at least one of the established conditions is not met, the inspection is postponed to another date, until which the homeowner is obliged to fulfill all the requirements.

If the requirements are not met properly, the gas company reserves the right to refuse gasification of a particular apartment.

So, gas equipment is equipped with special caps, while the object can be connected to gas only if the owner of the property fulfills all the requirements in accordance with the norms of the document SP 42-101-2003 "General provisions for the design and construction of gas distribution systems from metal and polyethylene pipes".

Checking the fulfillment of requirements

The term of validity of the fire act is only 1 month, during which the employees of the technical supervision must connect the gas

The gas distribution company draws up the technical specifications, which is obliged to provide the owner of the home with the relevant document within 14 days after the application is submitted. After checking the fulfilled requirements, it is better to order the project from the company that the gas company advises, since this is the only way to speed up the process of connecting the gas.

When is the connection made?

Gas start-up is carried out only if the owner of an apartment in an apartment building has passed all the established stages, including the repair of the premises and conclusion of a contract with a service company, a gas supplying organization.

An important condition is the passage of a planned briefing that highlights all the most important points for the safe use of gas equipment.

Inspection of indoor gas equipment

Gas connection is made only if all the established requirements have been fulfilled by at least 50% of the residents of the apartment building

If the homeowners are determined with the exact date, then the specialists of the gas company will be able to conduct pressure testing of gas networks in apartments that belong to the same riser. To do this, employees will need access to each apartment, otherwise the crimping will have to be postponed to another date.

This is the most important condition before the direct connection of the facility to the central gas pipeline, since it is often at this stage that gas leaks are detected.

In the event of a malfunction in the operation of the gas equipment, the employees of the gas service will carry out all the necessary work to eliminate them. After successful pressure testing, the gas start-up date will be announced to the residents of the apartment building. On this day, all apartment owners must also be at home in order to provide access to intra-apartment gas equipment.

Basic rules for gasification in an apartment

In the process of drawing up individual technical specifications, the purposes of gas use by the owner of the apartment are taken into account, including the number of gas appliances installed. It is on the basis of this information that a list of requirements is drawn up.

Equipment check before gas connection

GorGaz employees do not always include in the technical specifications mandatory rules for the installation of gas equipment, therefore, due to their failure, the employee of the Ministry of Emergency Situations will be forced to postpone the date of connection gas

You can familiarize yourself with the established rules for installing gas equipment inside an apartment in the document SP 42-101-2003 "General provisions for the design and construction of gas distribution systems made of metal and polyethylene pipes ”.

According to the document, there are a number of minimum requirements established for all gas consumers:

  • painting the gas pipe white;
  • ensuring the sealing of the chimney installation site using cement mortar;
  • installation of the grill on the ventilation duct;
  • installation of a kitchen door with a 3 cm undercut from the floor, and installation of a decorative grille at a distance of 10 cm from the floor;
  • installation of electrical outlets next to the boiler, and a signaling device located in the area of ​​the gas meter;
  • purchase of a voltage stabilizer for the boiler;
  • mandatory purchase of a gas stove before the inspection by an inspector;
  • connection of gas-using equipment using stainless steel hoses, no more than 1.5 m long;
  • purchase of a gas stove equipped with a gas control system;
  • availability of all the necessary technical documentation for the used gas equipment.

Non-compliance of gas-using equipment with elementary technical requirements is already a reason for refusal to conclude an agreement on the part of the gas supply service.

In order not to slow down the process of connecting gas in an apartment, it is important to fulfill all the established requirements in advance, and only after that call a specialist for an inspection.

Gas sensor installation example

For all residents of an apartment building, the installation of indoor gas monitoring sensors from June 6, 2019 is mandatory

Another prerequisite is the installation in the kitchen of a residential building of "easy-release" glass, while in the apartment building you will also need to install gas sensors.

Of course, such devices will require additional costs, but this will ensure safety not only for the owner of the apartment, but also for the residents of the entire apartment building.

Conclusions and useful video on the topic

You can learn about the unexpected difficulties of connecting gas in an apartment from the following video:

The procedure for connecting gas in an apartment consists of several important stages, failure to comply with which will entail refusal to carry out gasification by employees of the gas company. Even if the homeowner has fulfilled all the technical conditions established by the company, and has entered into an agreement with the gas supply company, the process of connecting the gas may be suspended.

For a successful check of gas equipment and subsequent gas connection, all residents of an apartment building must be at home in order to provide access to each apartment. At the final stage, it is important for all residents of the house to cooperate, which will allow gas workers to successfully connect gas to a residential building.

If you already had to go through all the stages of connecting gas in an apartment, you can share your experience in the comments under the article. Tell our readers what difficulties you encountered in the process of cooperation with the gas company, and what mistakes you had to correct while meeting the technical conditions.

Pressure reducer for a gas holder device, principle of operation, adjustment and instructions for replacement

Pressure reducer for a gas holder device, principle of operation, adjustment and instructions for replacementGasificationGas Equipment

Would you agree that when designing and installing gas equipment, the parameter that deserves special attention is the working pressure? Since only if the required values ​​are observed and this ch...

Read More
The gas column ignites and goes out: why the column goes out during operation and how to fix it

The gas column ignites and goes out: why the column goes out during operation and how to fix itGasificationGas Equipment

We are already accustomed to frequent breakdowns of washing machines, microwave ovens, dishwashers, air conditioners, vacuum cleaners, refrigerators. But relatively simple and well-designed technic...

Read More
A gas oven does not bake well: what to do if the oven does not bake from below and from above

A gas oven does not bake well: what to do if the oven does not bake from below and from aboveGasificationGas Equipment

In order for the dish to be well cooked, it is necessary to select the required temperature for cooking. But, what to do if the gas oven does not bake well with a properly selected temperature regi...

Read More